Skip to main content
DRR — Disaster Recovery Restoration
Emergency ServicesSchedule an Inspection
Leadership: Decades of Large-Loss Experience IICRC Certified Firm HAZWOPER ICRA 2.0 Class III-V AZ ROC #349012 AZ ROC #365125 — CR-42 Roofing EMR 0.97 — Workers' Comp Safety Leadership: Decades of Large-Loss Experience IICRC Certified Firm HAZWOPER ICRA 2.0 Class III-V AZ ROC #349012 AZ ROC #365125 — CR-42 Roofing EMR 0.97 — Workers' Comp Safety

Authority · Property Owner Reference

Post-Loss Claim Timeline.
What actually happens, hour by hour.

If you’ve never been through a property loss claim before, the uncertainty is the worst part of the first 48 hours. This page walks through what actually happens at each phase — from the dispatcher’s first call through the final close-out walkthrough — so property owners, property managers, and facility leadership can set the right expectations with tenants, family, or the executive team while the work is underway.

The six phases of a typical loss

Every loss runs through these phases in roughly this order. Small Cat 1 events compress all six into 2-3 weeks; large-loss commercial events stretch to 30-90+ days.

Hour 0

First call to dispatch

Triage on the phone — loss type, severity, access, contamination state. Dispatcher identifies the right crew + equipment. PM en route with a 60-minute on-site target across Phoenix Metro.

Hour 1–24

Mitigation

Stop the loss from getting worse. Water extraction, board-up, tarp, source isolation. IICRC Category / Condition / soot type determination logged as the first entry in the field record. Day-one photo timeline captured before any disruption.

Day 1–3

Carrier engagement

Property owner opens the claim with the carrier; adjuster assigned (sometimes a TPA — Contractor Connection / Alacrity / Code Blue). DRR's PM works directly with the adjuster from here, providing field-log access and answering coverage questions.

Day 1–14

Drying / containment / remediation

Equipment runs. Daily psychrometric or pressure-differential log delivered to the carrier. Materials past their salvage threshold (Cat 2/3 drywall, mold-affected assemblies, fire-damaged framing) get controlled-demolitioned and disposed per regulated-waste protocol. Independent IEP clearance testing on Cat 3 / Condition 3 work before the next phase begins.

Day 7–60+

Reconstruction

Drywall, paint, flooring, finish carpentry, like-kind-and-quality material match. Self-performed under AZ ROC #349012 KB-1 Dual — same DRR project manager throughout, no contractor handoff. Timeline is the most variable phase: small losses wrap in days, large-loss commercial in weeks-to-months.

Final

Close-out

Final walkthrough with the property owner / manager. Signed completion document. Full claim packet (sketch, photo timeline, drying log, clearance reports, F9-noted Xactimate scope) delivered to both the property owner and the carrier — the same file each side reads.

Technical References

Going deeper at each phase

Frequently Asked Questions

How fast does DRR actually arrive?

60-minute on-site target across Phoenix Metro. The first hour is the difference between Cat 1 and Cat 2 water — every hour delayed pushes you closer to the next contamination tier and bigger demolition. The dispatcher who answers your call is gathering the data the field crew needs: loss type, severity, access, current contamination state. By the time the truck arrives, the project manager already knows which equipment to bring.

What happens in the first 24 hours?

Mitigation phase. The crew stops the loss from getting worse: extracts standing water, tarps the roof, boards up windows, isolates the source. The IICRC Category determination (S500 Cat 1 / 2 / 3 for water, Condition 1 / 2 / 3 for mold, soot type for fire) gets logged as the first entry in the field record. Day-one photos are taken before any disruption. Drying or containment equipment gets installed.

When does the insurance carrier get involved?

Usually within the first 24 hours. The property owner opens the claim with their carrier (or the property manager does, for commercial). The carrier assigns an adjuster who may visit on-site or do a desk review. DRR's project manager works directly with the adjuster from there: confirming the scope, providing field-log access, answering coverage questions. On large losses the carrier may also assign a TPA (Contractor Connection, Alacrity, Code Blue) — DRR is an enrolled vendor on those networks.

How long does drying take?

Depends on the IICRC S500 Drying Class (1-4 — see /authority/drying-classes-1-4). Class 1 (small area, low porosity) might dry in 2-4 days. Class 2 (whole room) typically 3-5 days. Class 3 (top-down saturation) 5-10 days. Class 4 (specialty / deep-cavity) 7-21+ days. Daily psychrometric readings (temperature, relative humidity, grains-per-pound) document progress. Adjusters expect the daily log as part of the claim file.

What's the difference between mitigation and reconstruction?

Mitigation stops the loss from getting worse and dries / decontaminates the affected materials — first 1-3 weeks typically. Reconstruction rebuilds what was removed: drywall, paint, flooring, cabinetry, finish carpentry — often weeks to months after mitigation completes. They're priced as separate Xactimate categories. DRR self-performs both under AZ ROC #349012 KB-1 Dual, so single project manager from first call to final walkthrough — no contractor handoff. See /authority/restoration-vs-remediation for the full glossary.

When do I need a mold or biohazard subcontractor?

If the loss escalated past Cat 1 water, or if the building has pre-existing mold, or if there's a biohazard component (sewage, trauma, etc.), DRR runs the S520 (mold) / S500 Cat 3 (sewage) protocols in-house. We don't subcontract these phases — the same project manager runs them with HAZWOPER-certified crews. See /authority/sewage-cat3-protocols and /authority/mold-conditions for the protocols.

What's a supplement, and when does one get filed?

A supplement is a revised estimate filed when conditions discovered during work require additional scope beyond the original estimate. Common triggers: hidden mold revealed during demolition, moisture migration into adjacent assemblies, concealed building materials, or structural damage exposed during pack-out. Supplements should be filed within 72 hours of discovery with photos and field-log evidence. DRR files supplements proactively with documentation already attached, which is why most clear first-pass review.

What documentation will I get at close-out?

A complete claim packet: the Xactimate scope with sketch and F9 notes, IICRC Category / Condition / Class determinations, day-one through close-out photo timeline, daily psychrometric drying log (water losses) or pressure-differential log (mold / Cat 3 containment), post-drying moisture map showing dry-standard achieved, third-party clearance test results when applicable, and a signed close-out letter. Same packet the carrier received — your file matches the claim file.

How does DRR handle direct billing vs. me paying upfront?

Direct billing to the carrier is standard for covered losses — DRR submits the scope and waits on the carrier check. The property owner is responsible for the deductible and any non-covered scope. For non-insurance work (preventive care, owner-funded repairs), DRR invoices on standard commercial terms. The first conversation with dispatch covers payment posture so there are no surprises.

What's the typical total timeline from first call to close-out?

Highly variable. A small Cat 1 water loss in a single bathroom might wrap in 2-3 weeks total (mitigation + drying + reconstruction). A large-loss commercial event with multi-floor scope, contents pack-out, and significant rebuild can run 30-90+ days. Healthcare with ICRA 2.0 containment, hospitality with phased reopening, or industrial with regulatory coordination can extend further. The variable that matters most for timeline is reconstruction scope — mitigation + drying is usually 1-3 weeks regardless of loss size.

Active loss right now? Skip the article.

The first hour is the difference between Cat 1 and Cat 2. Call dispatch — IICRC-certified crews mobilize immediately with a 60-minute on-site target across Phoenix Metro.

(602) 228-9494